A project uses predictive governance for regulatory milestones and agile delivery for application features. How should the manager integrate planning?
Published
- Allow each team to ignore shared milestone dependencies
- Require every feature to be fully specified before any iteration begins
- Connect iterative delivery forecasts and dependencies to required governance milestones
- Replace all formal milestones with an informal backlog