A project uses predictive governance for regulatory milestones and agile delivery for application features. How should the manager integrate planning?

Published
  1. Allow each team to ignore shared milestone dependencies
  2. Require every feature to be fully specified before any iteration begins
  3. Connect iterative delivery forecasts and dependencies to required governance milestones
  4. Replace all formal milestones with an informal backlog