A project uses scarce specialists inefficiently because incomplete inputs repeatedly interrupt their work. What should the manager improve?

Published
  1. Require specialists to ignore missing requirements
  2. Increase specialist assignments without fixing inputs
  3. Readiness criteria and sequencing before scarce-resource work begins
  4. Measure only hours charged