A project uses scarce specialists inefficiently because incomplete inputs repeatedly interrupt their work. What should the manager improve?
Published
- Require specialists to ignore missing requirements
- Increase specialist assignments without fixing inputs
- Readiness criteria and sequencing before scarce-resource work begins
- Measure only hours charged