A project's benefits will be measured six months after the team disbands. What should be established at transition?
Published
- An accountable benefit owner, measures, baseline, and follow-up arrangement
- A rule that all benefits are realized at code completion
- A requirement that the project manager remain assigned indefinitely
- Deletion of the business case at closure