A project's benefits will be measured six months after the team disbands. What should be established at transition?

Published
  1. An accountable benefit owner, measures, baseline, and follow-up arrangement
  2. A rule that all benefits are realized at code completion
  3. A requirement that the project manager remain assigned indefinitely
  4. Deletion of the business case at closure