A proposed integration date depends on an external release whose owner has not committed. What should the manager do?

Published
  1. Add hidden contingency without explaining the assumption
  2. Validate the dependency and reflect its uncertainty in the integrated forecast
  3. Report the date as guaranteed because it appears in a slide
  4. Remove the external work from the dependency map