A proposed integration date depends on an external release whose owner has not committed. What should the manager do?
Published
- Add hidden contingency without explaining the assumption
- Validate the dependency and reflect its uncertainty in the integrated forecast
- Report the date as guaranteed because it appears in a slide
- Remove the external work from the dependency map