A proposed story combines payment, shipping, and reporting changes that cannot fit one iteration. What is the best next step?
Published
- Split only into database, interface, and test phases with no usable result
- Remove the estimate to make it fit
- Declare the whole story Done when the first component finishes
- Split it into smaller coherent value slices while managing dependencies
Comments — 0