A quality audit finds that teams follow an outdated procedure despite a current approved standard. What should be addressed?

Published
  1. Only the number of completed inspections
  2. Procedure control, communication, and actual operating adoption
  3. A claim that every deliverable is defective
  4. Only the supplier's market position

Comments — 0