A regulated component passes a demonstration but lacks required traceable test records. What should the manager do?

Published
  1. Ask the team to recreate historical results from memory
  2. Verify and complete the required evidence before claiming acceptance readiness
  3. Treat applause at the demonstration as the required record
  4. Remove the record requirement without approval