A retrospective identifies the same action repeatedly, but it is never implemented. What should the manager facilitate?

Published
  1. A rule that retrospectives may not discuss prior actions
  2. A claim that documenting the action is sufficient
  3. A specific owner, feasible commitment, and review of the improvement result
  4. A longer list of additional ideas