A retrospective identifies the same action repeatedly, but it is never implemented. What should the manager facilitate?
Published
- A rule that retrospectives may not discuss prior actions
- A claim that documenting the action is sufficient
- A specific owner, feasible commitment, and review of the improvement result
- A longer list of additional ideas