A risk estimate depends heavily on a supplier's unverified claim about capacity. What should the manager do?
Published
- Report the estimate as exact because a spreadsheet calculated it
- Add hidden padding without noting the assumption
- Validate the assumption and communicate the effect of uncertainty on the forecast
- Remove the supplier from the risk model