A scarce test environment is required by two activities that were planned concurrently. What should the manager assess?

Published
  1. Assume logical independence means resources cannot conflict
  2. Resource-constrained sequencing and its effect on float and completion dates
  3. Mark both activities complete when either one uses the environment
  4. Reduce each activity's acceptance criteria without approval