A schedule links painting to plaster completion with a two-day drying period after plaster finishes. How is that waiting period best represented?

Published
  1. A two-day lead
  2. A finish-to-start relationship with a two-day lag
  3. Two days of negative float in every case
  4. A start-to-start relationship with no lag