A specialist is allocated at 120% across two projects. What should the manager do?
Published
- Count the same hours twice as contingency
- Remove the specialist's name from one schedule but keep the work
- Keep both schedules unchanged and assume extra effort
- Resolve the allocation with the resource owner and update feasible commitments