A specialist is allocated at 120% across two projects. What should the manager do?

Published
  1. Count the same hours twice as contingency
  2. Remove the specialist's name from one schedule but keep the work
  3. Keep both schedules unchanged and assume extra effort
  4. Resolve the allocation with the resource owner and update feasible commitments