A sponsor asks for an earlier release. Team members say the proposed workload is unsustainable and will increase defects. What should the manager do?
Published
- Promise the date and require indefinite overtime
- Reject any release discussion because the original date was approved
- Analyze feasible scope, sequencing, and capacity options with the team and discuss tradeoffs
- Remove quality checks to make the schedule appear achievable