A sponsor asks for an earlier release. Team members say the proposed workload is unsustainable and will increase defects. What should the manager do?

Published
  1. Promise the date and require indefinite overtime
  2. Reject any release discussion because the original date was approved
  3. Analyze feasible scope, sequencing, and capacity options with the team and discuss tradeoffs
  4. Remove quality checks to make the schedule appear achievable