A sponsor asks to overlap design and construction to shorten a critical path. What should the manager explain?

Published
  1. Fast tracking always reduces cost and risk together
  2. Adding more workers is the defining feature of fast tracking
  3. Overlapping noncritical tasks guarantees an earlier project finish
  4. Fast tracking can reduce duration but can increase rework and coordination risk