A sponsor asks to overlap design and construction to shorten a critical path. What should the manager explain?
Published
- Fast tracking always reduces cost and risk together
- Adding more workers is the defining feature of fast tracking
- Overlapping noncritical tasks guarantees an earlier project finish
- Fast tracking can reduce duration but can increase rework and coordination risk