A sponsor asks whether the project is healthy. Which two evidence types best complement schedule and cost indices? Select 2 answers.
Published
- Current material risks and forecast assumptions
- Only positive stakeholder comments
- Acceptance and integrated product-quality evidence
- The number of status slides as proof of readiness
- The number of tasks started regardless of completion