A sponsor asks whether the project is healthy. Which two evidence types best complement schedule and cost indices? Select 2 answers.

Published
  1. Current material risks and forecast assumptions
  2. Only positive stakeholder comments
  3. Acceptance and integrated product-quality evidence
  4. The number of status slides as proof of readiness
  5. The number of tasks started regardless of completion