A sponsor assumes a pilot includes global rollout, while the approved scope covers one region. What should the manager do?
Published
- Change the status report to imply global completion
- Reject the sponsor's concern without discussion
- Quietly expand rollout to avoid disappointment
- Clarify the expectation gap using the approved objective and evaluate any requested expansion