A sponsor assumes a pilot includes global rollout, while the approved scope covers one region. What should the manager do?

Published
  1. Change the status report to imply global completion
  2. Reject the sponsor's concern without discussion
  3. Quietly expand rollout to avoid disappointment
  4. Clarify the expectation gap using the approved objective and evaluate any requested expansion