A sponsor wants to know whether an automated claims system delivers its promised savings after handover. What should be established during planning?

Published
  1. A project task count as the sole savings measure
  2. A rule that all benefits are realized at technical acceptance
  3. Benefit measures, a benefit owner, baselines, and a post-transition measurement approach
  4. A requirement to stop all measurement at project closure