A staged rollout can deliver value early but requires extra transition effort. What should the manager compare?
Published
- Only the first deployment's cost
- Incremental benefits, transition costs, dependencies, and risk for the rollout options
- Only the largest possible feature count
- A presumption that staged delivery is always superior