A stakeholder opposes a change because a previous rollout caused severe operational disruption. What should the manager do first?
Published
- Send only promotional material describing benefits
- Ask the sponsor to mandate enthusiasm before discussion
- Understand the stakeholder's concerns and incorporate relevant transition needs into planning
- Label the stakeholder resistant and exclude them from reviews