A stakeholder's influence increases after a reorganization. What should the manager update?

Published
  1. Stakeholder analysis, decision relationships, and the engagement approach
  2. Only the stakeholder's email signature in old documents
  3. The project budget automatically by a fixed percentage
  4. Nothing because the person is already listed