A steering committee asks whether to continue a project after a major supplier failure. What information best supports its decision?

Published
  1. Only the original business case with no revised assumptions
  2. Only the money already spent
  3. Updated options with expected value, costs to complete, risks, and contractual consequences
  4. Only the project manager's preferred outcome