A steering committee receives positive status, while frontline users report severe disruption. What should the manager do?
Published
- Reconcile the evidence and include operational outcomes in stakeholder reporting
- Continue positive reporting until the next phase ends
- Replace user feedback with task completion counts
- Assume the most senior stakeholder's view is always correct