A supplier-delivery risk has a defined trigger and funded contingency. The trigger occurs. What should the manager do?

Published
  1. Spend the contingency on unrelated scope
  2. Wait until the delivery is missed completely before considering the plan
  3. Record the risk as avoided merely because a plan exists
  4. Activate the planned response through the agreed authority and monitor its effect