A supplier-delivery risk has a defined trigger and funded contingency. The trigger occurs. What should the manager do?
Published
- Spend the contingency on unrelated scope
- Wait until the delivery is missed completely before considering the plan
- Record the risk as avoided merely because a plan exists
- Activate the planned response through the agreed authority and monitor its effect