A supplier reports a likely delay. The contract includes remedies and notification requirements. What should the manager do before invoking a remedy?

Published
  1. Review the contract and assess delivery impact with procurement and relevant stakeholders
  2. Promise the supplier that all penalties are waived
  3. Withhold every payment immediately without reviewing terms
  4. Ignore the delay until the contractual delivery date passes