A supplier reports that a required component will be discontinued before support handover. What should the manager assess?

Published
  1. Only whether the component arrived on time
  2. Assume the project ends before any support consequence matters
  3. Replace every component immediately without analysis
  4. Contractual commitments, viable alternatives, lifecycle support, and integrated impact