A supplier's representative promises a capability beyond the signed agreement. The customer expects it at launch. What should the manager do?

Published
  1. Tell the customer nothing until launch
  2. Treat the verbal promise as guaranteed without review
  3. Clarify the commitment and evaluate contractual and delivery implications with the authorized parties
  4. Automatically remove the supplier without assessing alternatives