A team adds an attractive feature without stakeholder prioritization because spare capacity appears available. What should the manager address?

Published
  1. Cancel all remaining work immediately
  2. Accept it automatically because no one complained
  3. Ask the team to conceal the feature until demonstration
  4. Validate the feature's value and priority through the agreed scope process