A team has an approved high-level plan, but detailed work six months away remains uncertain. What should the manager use?
Published
- A permanent ban on revising estimates
- No planning beyond the current day
- Rolling-wave planning with near-term detail and later refinement
- Exact task commitments for all future work based on guesses