A team has an approved high-level plan, but detailed work six months away remains uncertain. What should the manager use?

Published
  1. A permanent ban on revising estimates
  2. No planning beyond the current day
  3. Rolling-wave planning with near-term detail and later refinement
  4. Exact task commitments for all future work based on guesses