A team has completed low-priority work while the most important dependency remains unresolved. What should the manager facilitate?

Published
  1. Continue selecting only easy tasks to maintain a green chart
  2. Declare the dependency outside the project plan
  3. Reassessment of priority, constraints, and actions needed to unlock the valuable outcome
  4. Increase the number of status colors