A team has completed low-priority work while the most important dependency remains unresolved. What should the manager facilitate?
Published
- Continue selecting only easy tasks to maintain a green chart
- Declare the dependency outside the project plan
- Reassessment of priority, constraints, and actions needed to unlock the valuable outcome
- Increase the number of status colors