A team identifies a possible import restriction that could delay equipment. A specialist is assigned to monitor legislation and activate an alternate sourcing plan if a trigger occurs. What does this illustrate?

Published
  1. An issue that has already occurred
  2. A risk response with an owner, trigger, and contingency action
  3. An approved scope increase
  4. Automatic risk elimination through documentation