A team identifies a possible import restriction that could delay equipment. A specialist is assigned to monitor legislation and activate an alternate sourcing plan if a trigger occurs. What does this illustrate?
Published
- An issue that has already occurred
- A risk response with an owner, trigger, and contingency action
- An approved scope increase
- Automatic risk elimination through documentation