A team member with unique skills is unavailable for a planned activity. What should the manager evaluate first?
Published
- Delete the activity from scope unilaterally
- Promise the original date before examining options
- Qualified alternatives, sequencing options, and the effect on the delivery plan
- Assign the work to an unqualified person without support