A team's impediment requires another department to change a process beyond the team's authority. Which two actions are appropriate? Select 2 answers.
Published
- Require the team to bypass the mandatory process secretly
- Treat the impediment as irrelevant because it is external
- Engage the accountable department with evidence of the delivery impact
- Promise a resolution date before the responsible owner agrees
- Use the defined escalation path if the team cannot resolve it directly