A vendor offers a lower price if the project removes acceptance testing. What should guide the response?
Published
- Evaluate the proposal against required quality, risk, and contractual obligations
- Accept automatically because the budget decreases
- Ask the vendor to certify that testing is never needed
- Reject all commercial discussions without analysis