A vendor offers a lower price if the project removes acceptance testing. What should guide the response?

Published
  1. Evaluate the proposal against required quality, risk, and contractual obligations
  2. Accept automatically because the budget decreases
  3. Ask the vendor to certify that testing is never needed
  4. Reject all commercial discussions without analysis