A WBS includes development and testing but omits a required migration deliverable. What should the manager do?

Published
  1. Correct the scope decomposition and assess integrated planning effects
  2. Wait until operations discovers the gap after launch
  3. Treat the omission as proof that migration is unnecessary
  4. Hide migration under an unrelated task without updating the plan