A WBS includes development and testing but omits a required migration deliverable. What should the manager do?
Published
- Correct the scope decomposition and assess integrated planning effects
- Wait until operations discovers the gap after launch
- Treat the omission as proof that migration is unnecessary
- Hide migration under an unrelated task without updating the plan