All tasks are reported complete, but users cannot execute the core transaction across integrated components. What should status reporting emphasize?

Published
  1. Only the total number of closed tickets
  2. The team's confidence without demonstration
  3. Verified end-to-end acceptance and the remaining delivery gap
  4. A green status because each component passed a local test