An agile product forecast is based on eight Sprints of stable throughput, but an upcoming integration is new and uncertain. What should the manager communicate?

Published
  1. An exact guaranteed date derived solely from the average
  2. A date chosen by adding unlabelled hidden padding
  3. No forecast until all development is complete
  4. A forecast with assumptions and uncertainty, updated as integration evidence arrives