An estimate contains uncertain task durations and several converging dependencies. Leadership needs a probability-based completion range. Which technique is most suitable?
Published
- Schedule simulation using justified duration distributions and dependencies
- A rule that every task receives identical hidden padding
- A single best-case duration presented as guaranteed
- The arithmetic average of all task names' lengths