An increment has passed tests, but releasing it now would disrupt a customer's annual processing window. What should the manager do?

Published
  1. Evaluate release timing with the customer using value, readiness, and operating constraints
  2. Release automatically because tests passed
  3. Hold every future release indefinitely
  4. Change test results to justify a delay