An urgent security change is required during a deployment freeze. The organization has an emergency-change process. What should the manager use?
Published
- A permanent cancellation of all releases
- An undocumented change because security always removes approval duties
- The emergency process with the required authority, evidence, and follow-up
- The normal process even if it cannot address the active harm in time