Another project has a useful lesson about supplier onboarding. What should the manager do before adopting it?

Published
  1. Wait until the same failure occurs locally
  2. Reject all external lessons to preserve autonomy
  3. Use it unchanged solely because it succeeded elsewhere
  4. Assess its relevance and adapt it to the current context