Lessons from an earlier release are stored, but the next team repeats the same failure. What should the manager improve?

Published
  1. Only the repository's logo
  2. How relevant lessons are retrieved and incorporated into planning and working practices
  3. Only the number of lessons recorded
  4. A rule that no prior lesson may be challenged