Requirements are highly uncertain, and the buyer wants to pay for actual effort while actively managing the work. Which contract characteristic best fits this need?
Published
- A time-and-materials structure with appropriate limits and oversight
- A fixed price for fully defined work that does not yet exist
- A guarantee that all uncertain work has zero cost risk
- A purchase order with no rates or approval limits