Requirements for a new product are uncertain, but a mandatory external interface is stable. What planning approach is most suitable?

Published
  1. Use only the method preferred by the sponsor regardless of work characteristics
  2. Plan the stable interface requirements while iteratively elaborating uncertain product behavior
  3. Freeze every product detail before any user feedback
  4. Avoid all advance interface planning