Resource leveling moves a noncritical activity and causes a new longest path. What should the manager update?

Published
  1. Only the activity's display color
  2. The cost baseline automatically by the same percentage
  3. Nothing because the activity was originally noncritical
  4. The integrated schedule, critical path, and affected forecast