The operations team has the manuals but has not demonstrated recovery or support readiness. What is the best closure criterion?
Published
- Only the number of manual pages
- Only the timestamp of the handover email
- The project team's desire to move to another assignment
- Evidence that the agreed operating responsibilities can be performed