The operations team has the manuals but has not demonstrated recovery or support readiness. What is the best closure criterion?

Published
  1. Only the number of manual pages
  2. Only the timestamp of the handover email
  3. The project team's desire to move to another assignment
  4. Evidence that the agreed operating responsibilities can be performed