The team has delivered all approved features. Before formal closure, what should the manager verify?

Published
  1. Only that the launch announcement has been sent
  2. Only that every team member has stopped charging time
  3. Acceptance, outstanding obligations, transition readiness, and required closure records
  4. Only that the project budget has been fully spent