Two activities can run concurrently only if a second test rig is rented. What should support the decision?

Published
  1. The schedule benefit compared with rental cost, constraints, and other consequences
  2. The number of people attending the planning meeting
  3. A rule that all parallel work is preferable
  4. The rental price alone without considering delay