Two specialists propose incompatible designs. Both satisfy minimum requirements, but their tradeoffs affect reliability and operating cost. What should the manager facilitate?
Published
- A private decision based solely on which specialist is more persuasive
- Postponement until construction forces a choice
- A decision using agreed evaluation criteria, evidence, and accountable participation
- Immediate compromise by implementing half of each design