Two specialists propose incompatible designs. Both satisfy minimum requirements, but their tradeoffs affect reliability and operating cost. What should the manager facilitate?

Published
  1. A private decision based solely on which specialist is more persuasive
  2. Postponement until construction forces a choice
  3. A decision using agreed evaluation criteria, evidence, and accountable participation
  4. Immediate compromise by implementing half of each design