A backlog contains many obsolete requests after a strategy change. What should the Product Owner do?

Published
  1. Retain every request as a mandatory commitment forever
  2. Hide the obsolete requests in a separate unofficial queue
  3. Ask Developers to implement them in arrival order
  4. Make the backlog reflect the current goal and useful future work

Comments — 0