A company appoints three Product Owners with equal authority over one product backlog. Which Scrum principle is violated?

Published
  1. Only Developers may order the Product Backlog
  2. Stakeholders cannot advise the Product Owner
  3. The Product Owner is one person, not a committee
  4. Every product must have three separate backlogs